Precharge and Contactor Control [SOLVED]
- Renegate2020
- Posts: 50
- Joined: Tue Dec 01, 2020 6:20 am
- Location: Odessa UA
- Has thanked: 1 time
- Contact:
- E46Driver
- Posts: 32
- Joined: Fri Sep 17, 2021 3:51 am
- Location: Alberta
- Has thanked: 2 times
- Been thanked: 5 times
Re: Precharge and Contactor Control
Sounds like it should be reliable. I have done the same. Hope to never have to worry about it again!
Re: Precharge and Contactor Control
Was there any general conclusion to this?
Were @E46Driver’s issues related to the added peripheral equipment, or to the Leaf Gen 2 board (alt the mainboard)?
Would you advice to add a 1 sec delay to the main contractor just to be safe, or is it just needed under certain circumstances?
Were @E46Driver’s issues related to the added peripheral equipment, or to the Leaf Gen 2 board (alt the mainboard)?
Would you advice to add a 1 sec delay to the main contractor just to be safe, or is it just needed under certain circumstances?
-
- Posts: 265
- Joined: Mon Jul 03, 2023 3:17 pm
- Location: CT, central shoreline, USA
- Has thanked: 92 times
- Been thanked: 65 times
Re: Precharge and Contactor Control
For those of you with this early pulse, did newer versions of the code eliminate it? Trying to follow up on this for the gen 3 leaf adapter board. Looking into implementing the suggestions listed here but I don't want to add delays to the contactors if it's not an issue.